"Used for Weapons storage": There was a problem at the Kursk NPP on the power unit - the media
The station's press service stated that one of the two turbogenerators of the power unit was disconnected to eliminate the signs of bearings. The Kursk Nuclear Power Plant (NPP) reduced the power of power unit # 2 by 50% to troubleshoot the problems that have arisen. About it reports the Russian news agency "Interfax" with reference to the press service of the nuclear power plant. "The power of the power unit №2 of Kursk NPPs was reduced to 500 MW.
On July 29, at 08:51, the MSC staff of the blockboard of management in accordance with the operating regulation disconnected one of two turbogenerators from the network to eliminate the signs of bearings," the press service said. It should be noted that in the fall of 2022, the GUR stated that the Russian army was using the territory of Kursk NPPs and the enterprises associated with it to store C-300 missiles, and possibly Iranian ballistic missiles.